More Details Emerge on IBM's Upcoming Power6 Server Launch

Published: May 3, 2007

by Timothy Prickett Morgan

IBM, like most other server makers, doesn't like to talk about upcoming product launches because such talk can have an adverse effect on sales in the current quarter. That's one of the reasons why Big Blue is not talking about its upcoming Power6 server launch, and it is also why the company has done nothing to confirm or deny some of the rumors that are running around about Power6 being delayed. But if some of the sources I have heard from are right, then the Power6 launch is imminent.

Last week, I took a look at the rumors swirling around about the Power6 chip and its systems. Some rumors say Power6 will be delayed, and others that I am now hearing say IBM will crimp the clock speed back to 3.3 GHz or 3.5 GHz except for the machines that get sent to the big supercomputing laboratories operated by the U.S. Department of Energy. I have no confirmation of these new rumors, but IBM is expected to deliver a range of Power6 processors that span as low as 3 GHz and as high as 5 GHz over the two-year span of the product, which includes a Power6+ kicker. And given that this is a new chip architecture, it is possible that IBM cannot initially get the clock speeds as high as it wants with Power6. As I pointed out last week, this certainly happened with Power5 and Power5+, which were supposed to start at around 1.5 GHz and blow through 2.5 GHz and on up through 3 GHz and higher, but which have crested at 2.3 GHz.

Two independent sources, reading last week's story, sent me the same rumors that they are now hearing about Power6, which is that the chip and its systems will be launched sometime in late May for a June or July delivery. (One was specific enough to say that the launch would be at the Mohegan Sun resort in Connecticut, but that could just be a regional sales event for all I know.) Given this timing, which is toward the end of the second quarter when IBM doesn't want to be telling people to wait for new systems, just mentioning this rumor is going to give the salespeople at Big Blue apoplexy. But, IT Jungle works for the user community, not IBM. One source says the launch is in May with initial shipments in June, and said further that his IBM salesman said the Power6 clocks would hit 4.5 GHz in these machines. (Obviously, they can also be lower.)

With sales in the United States among enterprises falling off dramatically in March for both IBM and Sun Microsystems, IBM may be thinking that it is time to get the new Power6 boxes launched so it can prime the pumps for the third and fourth quarter. With Hewlett-Packard, Sun, and Fujitsu-Siemens all shipping midrange and high-end systems that can give Power5+ machines a serious run for the money, IBM needs to get its lead back in performance and bang for the buck as fast as it can.

A kind soul at one of the supercomputer labs gave me some hints about what the Power6 machines might look like, too, but this information is based on a presentation IBM gave at the end of last year; another source gave an updated presentation from only two months ago in 2007 that has the same information in it. In those presentations, there is a Power6 box called HV8 that that crams eight Power6 cores in a single 4U chassis, replacing the p5 550 and 550Q machines, which have two sockets and which can use Power5+ dual-core module (DCM) or quad-core module (QCM) packaging to deliver four or eight cores of processing power. Presumably this Power6 HV8 box is a four-socket box using DCMs, since the Power6+ kicker will have double the number of cores and will presumably do this by moving to QCMs. And both of these presentations clearly show that the initial Power6 chips in this box will run at 4 GHz or higher and that the Power6+ variant of this box will have clock speeds under 4 GHz. To make a QCM, you put two dual-core chips side-by-side and slow it down a little. So this follows.

Moving up the line is a Power6 box called IH, which will come in 16-core and 32-core variants with Power6 chips running at 4 GHz and higher. IBM will have some kind of water-cooling jackets on this puppy to keep it from overheating in the supercomputer labs. Rather than put QCMs in this box for the Power6+ generation, IBM will instead crank up the clock speed on the cores with the Power6+ chips, if this roadmap is still in effect.

The big, bad Power6 box, which was not given a code name, has up to 64 of the Power6 cores and will run at 4 GHz and higher. And with the Power6+ generation, IBM is expected to double the number of cores in the box to 128 to boost performance. It is unclear how IBM will do this. It could double the number of chips in the high-end multichip module (MCM) used in the biggest System p and System i servers, or it could double up the number of system boards.

With the Power7 generation, expected in 2010, IBM will once again double the core count in its servers, which seems to imply that Power7 will be a quad-core chip, not a dual-core chip like Power4, Power5, and Power6 were. The clock speeds on Power7 are expected to stay in the same 4 GHz and higher range, which means IBM can use the circuit shrinking that is enabled through improvements in chip fabrication to add more cores to the chip. This is the same tactic that Intel and Advanced Micro Devices are using as they move to true quad-core chips and they will continue it as they move further to octo-core designs.

All of these Power6 servers will support PCI-Express (also known as PCIe) peripherals, which provides a lot more bandwidth than the current PCI-X peripherals. IBM is also supporting the next generation of InfiniBand interconnect to lash servers together, and on the midrange Power6 IH systems, it will still support its "Federation" High Performance Switch interconnect.

There has been very little information about how entry Power6 servers might look like, and that is where most i5/OS and OS/400 shops will be interested. I'll find out what I can, and keep you posted.


RELATED STORIES

Power6: Later in 2007 Rather than Sooner?

Power6 Comes in 2007, No Slip into 2008 for the System p

IBM Bags System p5 Super Deals, But Is Power6 Slipping?

IBM Uncloaks Power6 Chip Details

Power6 Ups the Ante for Virtualization, Power Management

Power6 Gets Second Silicon, IBM to Crank the Clock



                     Post this story to del.icio.us
               Post this story to Digg
    Post this story to Slashdot


Sponsored By
MKS

You're at Bat, and It's Time for a "Change Up".
Change Up to MKS Implementer and MKS Integrity
for Application Lifecycle Management - Move to MKS NOW and SAVE!

Has the recent acquisition of your change management provider thrown you a curve ball?
Is your vendor offering you loosely coupled tools, leaving you with information gaps and a technical headache? Can your current change management solution meet your needs
today - and tomorrow?

This isn't slow pitch.

The world of software development is moving at a rapid pace and you need to be ready to meet new demands. Change management is a vital component of your business -- the foundation for compliance, for modernization, for process control and risk management. You need a vendor that can keep up with these business demands.

A winning team, less risk, more advantages.

Join a team that is reliable, steadfast and dedicated to delivering tangible business results to System i5 customers as well as cross-platform teams. MKS is firmly dedicated to the change management market and has a clear product roadmap. MKS's Implementer for software change management and deployment has a reputation of technical excellence with large and small customers across every industry.

Make the change up - move to MKS NOW and SAVE!

For a limited time MKS will help you make the move with special pricing when you purchase Implementer with MKS Integrity - giving you integrated workflow, complete audit trails and
coverage of the application lifecycle as well as a platform to manage both System i5 and
cross-platform development.

Visit the Products section of the MKS website for more information on
Implementer and MKS Integrity.

Click here to request more information on our time limited "change up" offer.

Download the white paper:
"Managing iSeries Development in the Application Modernization Era."

The time is now to make the switch.

Call MKS today at 1-800-613-7535 to discuss your options, and while you're at it, request a
FREE change management process assessment by our team of experts with over 40 years of experience in the midrange market.

Contact MKS Sales at 1-800-613-7535 or sales@mks.com
For more information, visit www.mks.com/solutions


Editor: Timothy Prickett Morgan
Contributing Editors: Dan Burger, Joe Hertvik,
Shannon O'Donnell, Timothy Prickett Morgan
Publisher and Advertising Director: Jenny Thomas
Advertising Sales Representative: Kim Reed
Contact the Editors: To contact anyone on the IT Jungle Team
Go to our contacts page and send us a message.

Sponsored Links

Vibrant Technologies:  Quality Used Servers, Storage & Networking Hardware at up to 80% off new
World Data Products:  FREE 84-page Unix/Midrange Server Spec Book
COMMON:  Join us at the Annual 2008 conference, March 30 - April 3, in Nashville, Tennessee


The Four Hundred
The i5 515 and 525: IBM's Competitive Analysis

More Details Emerge on IBM's Upcoming Power6 Server Launch

How to Build a Less Expensive i5 Developer Workstation

Mad Dog 21/21: Hearts and Minds

The Linux Beacon
Startup 3Leaf Systems Looks to Shake Up Server Virtualization

Sun's X64-Based Streaming Server Runs on Linux

More Details Emerge on IBM's Upcoming Power6 Server Launch

Mad Dog 21/21: Hearts and Minds

Four Hundred Stuff
MySQL Database Getting Closer Ties to the System i

BCD Bringing PHP Generation to WebSmart IDE

Quadrant Updates Forms Package, Content Management System

IBM Rolls Out LTO 4 Tape Drives and Libraries

Big Iron
Brazilian Game Site Chooses Hybrid Mainframe-Cell Platform

Top Mainframe Stories From Around the Web

Chats, Webinars, Seminars, Shows, and Other Happenings

Four Hundred Guru
Monitor for Specific Messages in RPG

Overcome the Page Control Limitations of iSeries Access Printer Emulation Sessions

Admin Alert: Dealing with i5 Critical Storage Errors, Part 2

System i PTF Guide
April 28, 2007: Volume 9, Number 17

April 21, 2007: Volume 9, Number 16

April 14, 2007: Volume 9, Number 15

April 7, 2007: Volume 9, Number 14

March 31, 2007: Volume 9, Number 13

March 24, 2007: Volume 9, Number 12

The Windows Observer
Microsoft Releases First Public Beta of 'Longhorn' Server

How To Build a Green Data Center

Strong Office 2007 Sales Push Microsoft to Record Profit

Startup 3Leaf Systems Looks to Shake Up Server Virtualization

Four Hundred Monitor
Four Hundred Monitor's
Full iSeries Events Calendar

THIS ISSUE SPONSORED BY:

MKS
Lakeview Technology
Roaring Penguin
Arkeia
Vibrant Technologies



TABLE OF CONTENTS
More Details Emerge on IBM's Upcoming Power6 Server Launch

Sun Boots Solaris 10 on "Rock" Sparc Processors

Startup 3Leaf Systems Looks to Shake Up Server Virtualization

Mad Dog 21/21: Hearts and Minds

But Wait, There's More:


Sun's Grid Utility Expands Beyond the United States . . . Scalent Adds AIX Support to Virtual Operating Environment . . . How To Build a Green Data Center . . . IBM Rolls Out LTO 4 Tape Drives and Libraries . . . Hitachi Boosts Enterprise-Class Hard Drives to 1 Terabyte . . . Blogs Hosting Malware, ScanSafe Says . . .

The Unix Guardian

BACK ISSUES





 
Subscription Information:
You can unsubscribe, change your email address, or sign up for any of IT Jungle's free e-newsletters through our Web site at http://www.itjungle.com/sub/subscribe.html.

Copyright © 1996-2008 Guild Companies, Inc. All Rights Reserved.
Guild Companies, Inc., 50 Park Terrace East, Suite 8F, New York, NY 10034

Privacy Statement