Gartner Predicts Half of Data Centers Will Run Out of Power by 2008

Published: December 6, 2006

by Timothy Prickett Morgan

If you don't think power and cooling issue is a problem with data centers, then you are either one of the lucky companies with only modest computing requirements or you have never lived with a server cluster. But the analysts at Gartner have jumped on the power and cooling bandwagon, and now say that half of the data centers in the world are going to run out of power by the end of 2008.

Maybe the situation is worse than I thought, then, when I wrote Lean, Mean Green Machines three years ago.

Gartner did not, by the way, literally mean that data centers would go dark in two years after blowing some fuses or melting under their own heat. What Gartner did say was that by the end of 2008, 50 percent of the data centers in the world would not have enough power to meet the power and cooling requirements of the high-density computing gear that vendors are increasingly peddling.

Last Friday, Gartner kicked off its 25th annual Data Center Conference, and power and cooling issues took center stage. "With the advent of high density computer equipment such as blade servers, many data centers have maxed out their power and cooling capacity," explained Michael Bell, a vice president for research at Gartner. "It's now possible to pack racks with equipment requiring 30,000 watts per rack or more in connected load. This compares to only 2,000 to 3,000 watts per rack a few years ago."

Compute density has some benefits, if used properly. If you install water jackets on the server racks and create a lights-out environment, you can build a much smaller, more efficient data center. Part of the problem is that air is a wickedly inefficient means of cooling hot computers, so using less dense servers in a much bigger data center is not exactly a way to avoid the hassle of dealing with denser computing. Either way, IT and facilities managers have to do a lot of cost/benefit analysis to try to figure out how to better deliver efficient and affordable computing.

During the air-cooled computing era, which I will say ran from the late 1970s through the late 2000s, the power requirements from all of the non-IT equipment in the data center accounted for about 60 percent of the total energy consumption related to the data center. This energy was consumed by fans, pumps, and other cooling components. Gartner says that as the power requirements of IT gear continue to grow, energy costs will become the second largest operating cost in 70 percent of the data centers worldwide by 2009, following the cost of people and well ahead the cost of the IT gear itself.

Gartner is expecting a lot of innovation in the next three years, which will marry systems monitoring and management with power and cooling monitoring and management, so companies can cope with both aspects of their computing infrastructure and run jobs in such a way as to maximize performance and minimize energy use. Bell also said in a report culled from presentations at the conference that "although the power and cooling challenges will not be a perpetual problem, it is important for data center managers to focus on the electrical and cooling issue in the near team, and adopt these best practices to mitigate the problem before it results in equipment failure, downtime and high remediation costs."

That sounds like wishful thinking. The power and cooling issue is here to stay, unless computing moves off silicon and onto something that allows a lot more performance for a lot less energy.


RELATED STORIES

The Hardware Foundry

The Balance of Server Powers

Lean, Mean Green Machines



Sponsored By
WOLF COMPUTER CONSULTING

Reliable service and affordable rates for all
of your business computing needs.

                                             * Network Design/Installation/Support
                                             * Network Printing/Digital Print Migration
                                             * Upgrades and Troubleshooting
                                             * Training
                                             * Graphic Design
                                             * Virus Removal
                                             * Consulting

Wolf is a Microsoft Certified Systems Engineer and
Microsoft Certified Systems Administrator.

Contact Wolf
Email: info@wolfconsult.net
Fax: 973-293-0100
Phone: 914-443-5534



Editor: Alex Woodie
Contributing Editors: Dan Burger, Joe Hertvik,
Shannon O'Donnell, Timothy Prickett Morgan
Publisher and Advertising Director: Jenny Thomas
Advertising Sales Representative: Kim Reed
Contact the Editors: To contact anyone on the IT Jungle Team
Go to our contacts page and send us a message.

Sponsored Links

Micro Focus:  Develop, extend and deploy applications with Server Express and Enterprise Server
OpenLogic:  Install, integrate, test, manage, and learn over 120 open source projects with BlueGlue
COMMON:  Join us at the Spring 2007 conference, April 29 - May 3, in Anaheim, California

 
THIS ISSUE SPONSORED BY:

Vision Solutions
World Data Products
MKS
Lakeview Technology
Wolf Computer Consulting



TABLE OF CONTENTS
Microsoft Completes the 'Triple Launch'

Dell Carves Out Energy-Efficient PowerEdge Server Line

Microsoft's Business Intelligence Plan for the Masses

AMD Creates Two-Socket Athlon FX Variant, Demos Quad-Core Opteron

But Wait, There's More:


Microsoft Unveils Expression Studio Design Tools . . . Sentillion Overhauls Remote Access Offering . . . Phishing, Zero-Days Top Symantec's Security List . . . eEye Launches Zero-Day Vulnerability Tracker . . . Gartner Predicts Half of Data Centers Will Run Out of Power by 2008 . . . Disk Array Sales Keep Revving in Q3, Says IDC . . .

The Windows Observer

BACK ISSUES

The Four Hundred
The System iWant, 2007 Edition

PwC Consultants Predict an IT Talent Shortage

Saving the System i: Fight Rather Than Switch

The X Factor: You Can't Steal What's Free, But You Can Pay a Lot for Something That Isn't Worth It

The Linux Beacon
Novell Previews Open Enterprise Server 2, Delays SLES 10 SP1

Hitachi Brings BladeSymphony Blade Servers to North America

AMD Creates Two-Socket Athlon FX Variant, Demos Quad-Core Opteron

As I See It: Behavioral Redlining

Big Iron
IBM's Last, Best Shot at the Big Iron Client

Top Mainframe Stories and Vendor Announcements

Chats, Webinars, Seminars, Shows, and Other Happenings

The Unix Guardian
Server Sales Perk Up a Little Bit in the Third Quarter

Cray, IBM Win Final Round of Giant DARPA HPCS Program

Sun Releases Java Under GPL Open Source License

As I See It: The Other "Tude"


 
Subscription Information:
You can unsubscribe, change your email address, or sign up for any of IT Jungle's free e-newsletters through our Web site at http://www.itjungle.com/sub/subscribe.html.

Copyright © 1996-2008 Guild Companies, Inc. All Rights Reserved.
Guild Companies, Inc., 50 Park Terrace East, Suite 8F, New York, NY 10034

Privacy Statement